Over its 52 years in business, Creative Contractors, Inc. of Clearwater has built schools, office buildings, hospital additions and more. Along the way, it developed a specialty in building, restoring and renovating performance halls and theaters.
The company recently completed the auditorium restoration and major infrastructure upgrades that are part of Tampa Theatre’s broader $24.5 million renovation, including the auditorium’s Mediterranean courtyard motif and the twinkling lights in its starry sky, now controllable LED lights.
The auditorium reopened in time for the theater’s 100th anniversary celebration last month. In recent years, the company also restored the theater lobby, replaced the seats in the auditorium and built the 43-seat Microcinema next door.
Currently, its crews are also reworking areas of Tampa’s Straz Center for the Performing Arts, adding restaurants, a rooftop bar and renovating theater lobbies. At St. Petersburg College’s Palladium Theatre, a popular performance hall in downtown St. Petersburg, other workers are replacing the seats and improving the acoustics.
“It’s an interesting niche that we have and it’s one that we’re grateful for, and we take particular pride in,” says Josh Bomstein, CEO and president of Creative Contractors.
The company, which was founded in 1974 by his father, Alan Bomstein, also restored the historic Nancy and David Bilheimer Capitol Theatre in Clearwater and built the Instructional Performing Arts Center at Pasco-Hernando State College.
Building a specialty in performing arts spaces
Creative Contractors gained early experience in the specialty when it undertook the first major renovation of Ruth Eckerd Hall in Clearwater more than 20 years ago. One particularly challenging aspect of that project was connecting the east and west lobbies.
“We had to remove all the seating and create the connection between the east and west lobbies and then rebuild over it a seating bowl.” Josh Bomstein says, adding that the side aisles are at an angle so every step was a different dimension.
“It gave us an understanding not only of working with theater, but with audio visual and acoustics and acousticians,” he says, noting that the experience provided the business with “a lot of smart solutions to offer clients in performing arts spaces.”
Tampa Theatre: Restoring 1926, preparing for 2026
For the Tampa Theatre project, Creative Contractors brought in EverGreene, a company specializing in restoring old buildings, to take the auditorium back to the way it looked 100 years ago. It replastered the walls, the entire ceiling and reproduced the original colors.
Bomstein: “I highly recommend going in and seeing the finished product.”
Jill Witecki, Vice President and Director of Marketing at Tampa Theatre, says a visitor who’s seen the auditorium before will find the colors and overall tone brighter. Most of the walls are now a butter yellow color, as she describes it. When the theater was first renovated 50 years ago, the walls were a duller brown color.
“What’s more important than what people are going to see when they walk in is what people aren’t going to see when they walk in, and that has to do with a lot of what’s behind the walls and behind the stage, upgrades to systems that have been outdated for decades,” she says.
Tampa Theatre was the first air-conditioned commercial building in town when it opened, and over the century upgrades were done piecemeal, a number of them during the late ’70s and early ’80s, she says. Now it has an all new system.
Workers completely overhauled the electrical, mechanical and plumbing. All of the theatrical systems, the lighting, sound and projection systems were upgraded or replaced.
“The way we’ve been describing it to people is when our guests walk in, we want them to see 1926. When a touring show walks in, we want them to see 2026,” Witecki says.
The company is still working on an education center, administrative offices and storage rooms. The focus was to have the main auditorium—called the Duncan Auditorium—ready for the anniversary celebration on Oct. 15.
“We’ve worked with Creative so many times now to such success that it was a pretty easy decision to bring them back in on this project,” Witecki says.
The Straz opens toward the Riverwalk
A few blocks away, a $100 million expansion and renovation of the Straz Center for the Performing Arts is underway and most of the work is expected to be completed by late next summer, Bomstein says.
Crews are expanding the Patel Conservatory by 30 percent, an educational and studio space for students, and they’re creating four new food and beverage venues—a fine dining restaurant, a cafe, rooftop bar and a bistro with affordable food options at the Riverwalk, adjacent to the new, expanded stage where free performances will be programmed, says Greg Holland, President and CEO of the Straz.
“Anyone can drop by, see a free performance, enjoy a burger or a salad, whatever they want.”
Within a few weeks, workers are expected to start installing a sculptural veil of perforated metal that will curve around the west and north walls over a terrace that extends to the Riverwalk.
“It’s going to be quite iconic,” Bomstein says.
The company has refurbished the lobbies of the Morsani and Ferguson Halls with new flooring, finishes, paint and lighting.
“Everything is just really brightened and lightened up,” Holland says.
A new sound for the Palladium
At the Palladium, the $13 million project is expected to be complete next August. It centers on a makeover of the 800-seat Hough Hall, the main performance hall in the building.
“It will be acoustically superior to what it has been,” Bomstein says. “The new seating will be much more comfortable than what it has been, and it will allow for a much better patron experience and certainly better for the performers.”
Paul Wilborn, Executive Director of the Palladium, says Creative Contractors was chosen out of bids from contractors throughout Florida and a couple of national companies, but that the company had been on their radar because of their work on Ruth Eckerd, Tampa Theatre and others.
The work is confined to inside the theater, he says, and will not affect the beautiful Romanesque Revival-style architecture of the building, constructed in 1925 as the First Church of Christ, Scientist.
Every seat in the theater will have a great view of the stage, Wilborn says. That wasn’t the case before.
Removing the pipe organ will create a new performance space above the stage. Double-pane windows will be installed to eliminate street noise.
Wilborn, a pianist and singer, is excited about the plan to improve the acoustics, which involves replacing the ceiling.
“We’re creating a thing that’s called variable acoustics, so that if we have an acoustic show it sounds one way. If we have a big amplified show, it sounds great as well,” he says. “We’re able to change the room and the acoustics of the room using some curtains and things that are part of this.”
Before, the sound was fine if performers were playing acoustic instruments, he says, but amplified music didn’t sound as good. Now it’s going to be a much better room for all types of music, he says.
“We were more like a church with a stage,” he says. “And now it’s going to be a real performing arts venue.”
To learn more, visit Creative Contractors.